In accordance with the requirements of SHDC Title 5, the following specific installation requirements are set forth in order to maintain a high level of quality control throughout the OSS construction process.

The SHD shall require certified installers to construct the OSS, except as noted under SHDC 5.45.050. In all cases, construction of the OSS shall include system back fill and final grading.

The installer shall:

A. Follow the approved design. Design revisions must have the concurrence of the designer and SHD before commencing work.

B. Have the approved design and permit in possession during installation.

C. Be on the site at all times during the construction of the on-site system.

D. Install the on-site system to be watertight, except for the disposal component.

E. Upon completion, post the permit on site in a conspicuous location until such time as the local Health Officer has granted final approval.

F. Cover the installation only after the local Health Officer has given approval to cover.

G. Back fill and grade the site to prevent surface water from accumulating over any component of the on-site system. [Res. 12-15. Prior code § 8.3 (Supplement)(VI)].